23. Complex real options (S23.6) Suppose you expect to need a new plant that will be ready...
Question:
23. Complex real options (S23.6) Suppose you expect to need a new plant that will be ready to produce turbo-encabulators in 36 months. If design A is chosen, construction must begin immediately. Design B is more expensive, but you can wait 12 months before breaking ground. Figure 23.9 shows the cumulative present value of construction costs for the two designs up to the 36-month deadline. Assume that the designs, once built, will be equally efficient and have equal production capacity.
Cumulative construction cost Total cost of design B Start A 0
Start B 12 Both plants would be ready at this time 24 36 Total cost of design A Time, months
◗ FIGURE 23.9 Cumulative construction cost of the two plant designs. Plant A takes 36 months to build; plant B, only 24. But plant B costs more.
A standard DCF analysis ranks design A ahead of design B. But suppose the demand for turbo-encabulators falls and the new factory is not needed; then, as Figure 23.9 shows, the firm is better off with design B, provided the project is abandoned before month 24.
690 Part Seven Options Describe this situation as the choice between two (complex) call options. Then describe the same situation in terms of (complex) abandonment options. The two descriptions should imply identical payoffs, given optimal exercise strategies.
Step by Step Answer:
Principles Of Corporate Finance
ISBN: 9781264080946
14th Edition
Authors: Richard Brealey, Stewart Myers, Franklin Allen, Alex Edmans