CAPM and Hurdle Rates. A project under consideration has an internal rate of return of 14 percent
Question:
CAPM and Hurdle Rates. A project under consideration has an internal rate of return of 14 percent and a beta of .6. The risk-free rate is 5 percent and the expected rate of return on the market portfolio is 14 percent.
a. Should the project be accepted?
b. Should the project be accepted if its beta is 1.6?
c. Why does your answer change?