a. Product A is made from three Bs and two Cs. Subassembly B is made from two
Question:
a. Product A is made from three Bs and two Cs. Subassembly B is made from two Es and one D. Subassembly C is made from one E and two Ds. Given this information and that below, fill in the MRP explosions for each of B, C, D, and E on the attached worksheet (lot sizes are minimums).
Product A has the following MPS values:
10 in week 3 20 in week 5 10 in week 6 30 in week 8 20 in week 10
b. The inventory specialist has just informed you that 140 of component E in inventory have a defect and must be scrapped. What actions do you need to take?