Complete the MRP records on the next page. Note the following: .. Production plans for the 800
Question:
Complete the MRP records on the next page. Note the following:
.. Production plans for the 800 Deluxe computer system are as follows:
.. Start assembling 2,500 kits in Week 2 .. Start assembling 3,000 kits in Weeks 3,4, and 5 .. Start assembling 2,000 kits in Week 6 .. The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements.
.. All scheduled receipts, lead times, and beginning inventory levels are shown.