The following bill of materials represents the major components for a computer system. Complete the MRP records
Question:
The following bill of materials represents the major components for a computer system.
Complete the MRP records below. Note the following:
■ Production plans (the MPS) for the 800 Deluxe computer system are as follows:
Start assembling 2500 in week 2
Start assembling 3000 in weeks 3, 4, and 5
Start assembling 2000 in week 6
■ The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements.
■ All scheduled receipts, lead times, and beginning inventory levels are shown.