The following bill of materials represents the major components for a computer system. Complete the MRP records

Question:

The following bill of materials represents the major components for a computer system.

Acme 800 Deluxe Computer System Speakers (2 needed) Monitor Keyboard | Packaging Installation System Unit Kit Cable Kit Complete the MRP records below. Note the following:

■ Production plans (the MPS) for the 800 Deluxe computer system are as follows:

Start assembling 2500 in week 2

Start assembling 3000 in weeks 3, 4, and 5

Start assembling 2000 in week 6

■ The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements.

■ All scheduled receipts, lead times, and beginning inventory levels are shown.

System Unit Lead time = 1 week Minimum order quantity = 500 Week 3 4 5 6. Gross Requirements 2500 3000 3000 3000 2000 Sc



Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Materials Management

ISBN: 978-9386873248

8th edition

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

Question Posted: