A work center has the following open and planned orders for week 4. Calculate the total standard

Question:

A work center has the following open and planned orders for week 4. Calculate the total standard time required (load).

Order Quantity Setup Time (hours) Total Time Run Time (hours/piece) (hours) Released Orders 125 200 0.50 0.10 345 70 0.7