A work center has two machines and two operators. The work center operates on two shifts and

Question:

A work center has two machines and two operators. The work center operates on two shifts and each operator works one shift at 8 hours per shift. The efficiency and utilization rates of the two machines and operators at this work center are 95% and 90%, respectively. The following table presents the work order to be completed in this work center on Friday of this week along with the information on the number of units to be produced, setup time, and the run time for each work order. Is there sufficient capacity available in this work center to complete all work orders? If not, what options would you suggest to mitigate the capacity overload?

Setup Time (in minutes) Run Time (in minutes/unit) Work Order # # of Units 702 8. 300 0.15 15 520 700 0.10 650 3,500 0.3

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: