It is Monday morning, and you have just arrived at work. Complete the following MRP record as
Question:
It is Monday morning, and you have just arrived at work. Complete the following MRP record as it would appear Monday morning. Lead time is 2 weeks, and the lot size is 100.
During the week, the following events occur. Enter them in the MRP record.
a. The planned order for 100 in week 1 is released.
b. Thirty of the scheduled receipts for week 1 are scrapped.
c. An order for 30 is received for delivery in week 3.
d. An order for 50 is received for delivery in week 6.
e. The gross requirements of 70 in week 1 are issued.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction To Materials Management
ISBN: 978-9386873248
8th edition
Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen
Question Posted: