Complete the following MRP record. The lead time is 4 weeks, and the lot size is 200.

Question:

Complete the following MRP record. The lead time is 4 weeks, and the lot size is 200. What will happen if the gross requirements in week 3 are increased to 150 units? As a planner, what actions can you take?

Initial MRP Week 2 3 4 5 Gross Requirements Scheduled Receipts Projected Available 100 Net Requirements Planned Order Re


Revised MRP Week 1 2 3 Gross Requirements Scheduled Receipts Projected Available 100 Net Requirements Planned Order Rece