Product A is an ATO product. It has a lot size of 150, and currently has an

Question:

Product A is an ATO product. It has a lot size of 150, and currently has an onhand inventory of 110 units. There is a 2-week demand time fence and a 12-week planning time fence. The following table gives the original forecast and the actual customer orders for the next 12 weeks:image text in transcribed

a. Given this information, develop a realistic master schedule, complete with ATP logic.

b. Tell how you would respond to each of the following customer order requests.
Assume these are independent requests, and do not have cumulative effects Also show what the master schedule would look like if the order was accepted:
" 20 units in week 3 " 40 units in week 5 " 120 units in week 7