From the following calculate the Material Variances; Actual production during the period 192 units. Material A Material
Question:
From the following calculate the Material Variances; Actual production during the period 192 units.
Material A Material B Actual Price per ton Rs. 277.50 Rs. 308 Standard Price per ton Rs. 240.00 Rs. 320 Actual Weight 16 tons 13 tons Budgeted production during the period 400 units for which the standard quantity of materials are 30 tons of A and 25 tons of B.
[Ans.: MCV = Rs.1,148 (Adv.); MPV = Rs.444 (Adv.) MUV = Rs.704 (Adv.)]
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Zero To Mastery In Accounting Become A High Level Accounting Manager
ISBN: 9789392475177
1st Edition
Authors: HECTOR ROBINETT
Question Posted: