Overhead variances, missing information. Dvent budgets 18,000 machine-hours for the production of computer chips in August 2009.
Question:
Overhead variances, missing information. Dvent budgets 18,000 machine-hours for the production of computer chips in August 2009. The budgeted variable overhead rate is $6 per machine-hour. At the end of August, there is a $375 favourable spending variance for variable overhead and a $1,575 unfavourable spending variance for fixed overhead. For the computer chips produced, 14,850 machine-hours are budgeted and 15,000 machine-hours are actually used. Total actual overhead costs are $120,000.
REQUIRED 1. Compute efficiency and flexible-budget variances for Dvent’s variable overhead in August 2009. Will variable overhead be overallocated or underallocated? By how much?
2. Compute production-volume and flexible-budget variances for Dvent’s fixed overhead in August 2009. Will fixed overhead be overallocated or underallocated? By how much?
LO1
Step by Step Answer:
Cost Accounting A Managerial Emphasis
ISBN: 9780135004937
5th Canadian Edition
Authors: Charles T. Horngren, Foster George, Srikand M. Datar, Maureen P. Gowing