Question:

5. The layout redesign of the pediatric ward is expected to take 47 weeks. The standard deviation of the critical path is 2.17 weeks. Find the z-values and determine the probabilities that:

a. The project will be completed within 50 weeks.

b. The project will take 49 weeks or longer.

c. The project will be completed within 40 weeks.

d. The project will be completed within 47 weeks.

e. The project will take 46 weeks or longer.