7. At BPH, the mean lead time demand for Gauze AX-7 was 70 boxes (normally distributed). The...

Question:

7. At BPH, the mean lead time demand for Gauze AX-7 was 70 boxes (normally distributed). The standard deviation of demand during lead time was 5. The manager of hospital supplies wants to maintain a 90% service level.

a. What safety stock level would you recommend?

b. What should the reorder point be?