7. Bradley Park Hospitals environmental services team wants to reduce patient room turnover times without sacrificing safety

Question:

7. Bradley Park Hospital’s environmental services team wants to reduce patient room turnover times without sacrificing safety and room cleanliness. Their first task involves identifying all the activities necessary to clean and disinfect a room after patient discharge and their respective durations (in minutes). Their efforts led to the following network diagram.

a. What is the time estimate for each activity?

b. Find the ES, EF, LS, LF, and S for each activity and determine the critical path.
How long does it take to clean and disinfect a room?

c. What is the probability of completing the room cleaning and disinfection process in 65 minutes and in 75 minutes?

d. What is the probability that the process will take longer than 77 minutes?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management In Healthcare Strategy And Practice

ISBN: 9780826126528,9780826126535

1st Edition

Authors: Corinne M. Karuppan , Nancy E. Dunlap,Michael R. Waldrum

Question Posted: