A small renovation of a Hard Rock Cafe gift shop has six activities (in hours). For the
Question:
A small renovation of a Hard Rock Cafe gift shop has six activities (in hours). For the following estimates of
a, m, and
b, calculate the expected time and the standard deviation for each activity: Activity a b ABCDEE 11 15 19 27 31 41 18 18 18 8 13 19 17 18 20 F 16 19 22