Given this information on planned and actual inputs and outputs for a service center, determine the work
Question:
Given this information on planned and actual inputs and outputs for a service center, determine the work backlog for each period. The beginning backlog is 12 hours of work. The figures shown are standard hours of work.
PERIOD 1 2 3 4 5 Input Planned 24 24 24 24 20 Actual 25 27 20 22 24 Output Planned 24 24 24 24 23 Actual 24 22 23 24 24