During 2007, Wildcat Oil Company constructed an offshore production platform at a cost of ($25,000,000.) A total
Question:
During 2007, Wildcat Oil Company constructed an offshore production platform at a cost of \($25,000,000.\) A total of 16 wells are planned. As of 12/31/07, only 2 out of the 16 wells had been drilled. Calculate DD&A given the following information.