Question: Archer Construction Company began work on a $420,000 construction contract in 2014. During 2014, Archer incurred costs of $278,000, billed its customer for $215,000, and
Archer Construction Company began work on a $420,000 construction contract in 2014. During 2014, Archer incurred costs of $278,000, billed its customer for $215,000, and collected $175,000. At December 31, 2014, the estimated future costs to complete the project total $162,000. Prepare Archer’s journal entry to record profit or loss using (a) the percentage-of-completion method and (b) the completed contract method, if any.
Step by Step Solution
3.43 Rating (159 Votes )
There are 3 Steps involved in it
a Percentage of com pletion Method Deb it Construction in Progress 162 ... View full answer