Computer Consultants (CCC) signed a contract in 2018 to develop a computer network system for Platinum Entertainment. Cosmo uses the percentage-of completion method and determines its measure of progress using the cost-to-cost approach. The firm provided the following information for 2018.
Contract price .......................................................................... $85,000
2018
Actual construction costs incurred during the year .......... $12,000
Estimated total costs ............................................................. 60,000
Progress billings made during the year .............................. 30,500
Cash collections during the year ......................................... 25,000
Compute the percentage completed, gross profit recognized, and the amount of the revenue recorded in 2018.