Repeat the requirements of P8-9 assuming Wayne Computer Consultants uses the completed-contract method to report its long-term contracts.

Data from P8-9

R. Wayne Computer Consultants, Incorporated develops and installs integrated computer systems and networks for large utilities. On January 2, 2018. The company signed a contract to deliver an electricity deployment system for a grid coveting three New England states. The contract paid R. Wayne a fixed Fee of $18,000,000. Wayne Computer Consultants uses the percentage-of-completion method (cost-to-cost approach) to report its long-term contracts. Other relevant information related to the contract is presented in the following table.

Contractpr ce $18,000,000 2018 $ 4,500 000 2019 2020 Actual construction costs incurred dur ng the year Construct on cos

Required

a. Compute the gross profit and revenue to be recognized each year of the contract.

b. Prepare the journal entries required for each year of the contract.

c. Prepare the t-accounts for construction in progress, billings on construction in progress, and accounts receivable.

d. Determine the net asset (liability) for each year o f the contract on December 31.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting

ISBN: 978-0134730370

2nd edition

Authors: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella

Question Posted: