As of December 31, 2024, Cady Construction has one construction job for which the construction in progress
Question:
As of December 31, 2024, Cady Construction has one construction job for which the construction in progress (CIP) account has a balance of $20,000, and the billings on the construction contract account has a balance of $14,000. Cady has another construction job for which the construction in progress account has a balance of $3,000, and the billings on the construction contract account has a balance of $5,000. Indicate the amount of contract asset and/or contract liability that Cady would show in its December 31, 2024, balance sheet.