An order for 50 of a product is processed on work centers A and B. The setup
Question:
An order for 50 of a product is processed on work centers A and B. The setup time on A is 45 minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction To Materials Management
ISBN: 978-9386873248
8th edition
Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen
Question Posted: