Question: Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 200. The demand time fence is 2
Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 200. The demand time fence is 2 weeks.

Week Forecast Customer Orders Projected Available Balance MPS 140 1 80 100 2 80 90 3 80 50 4 70 40