Answered step by step
Verified Expert Solution
Link Copied!
Question
1 Approved Answer

The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U.

The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.

*Construct a product structure. Identify all levels, parents, and components.

1. (Use the following grid to draw the product structure BOM)

1. Same scenario as above. (Use the following grid to draw the time-phased product structure). What is the overall lead time?

*Construct a product structure. Identify all levels, parents, and components.

2. Given the following BOM and available on-hand inventory, compute the new requirements for all the dependent items for a batch of 70 units of the Bracket.

Bracket Base Spring Clampa) Housingz) Clampa) Handlea Castinga) Bearingz Shafta) Handlea) Castinga)

Net Gross requirement Available requirement Bracket 70 Base 10 Spring 70 Clamp 130 Housing 130 Handle 50 Casting 40 Bear

3. Develop a complete net material requirements plan for the production of following MPS and prepare the ?exceptions? report.

Master production schedule

Week: 6. MPS for A 200 80 95 150 MPS for B 100 100 100 100 100

Data:

Lead Item time Available Scheduled Receipts 100 200 in week #1, 300 in week #2 D 400 400 in week #1, 300 in week #2 1300

Bill-of-Materials:

C2 D2 D1 D3 Ez E2 E2 Es Ez

Item : LT= GR = Week: Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned o

Item : LT = GR = Week: Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned

Item : LT= GR = Week: Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned o

4. Given setup cost of $300 per setup and holding cost of $2.00 per unit per week, develop lot sizes (a) Lot-for-lot, (b) EOQ, and (c) POQ. Determine the total cost for each method. Use lead time of one week.

(a) Lot-for-lot

LT= Week: 4 Gross requirement 40 25 40 45 45 50 45 30 Scheduled receipts Projected on-hand 50 Net Requirement Planned re

Total ending inventory =

No. of setup =

Carrying cost =

Setup cost =

Total cost =

(b) EOQ

LT= Week: 1 4 Gross requirement Scheduled receipts 40 25 40 45 45 50 45 30 Projected on-hand 50 Net Requirement Planned

Holding cost/week =

Setup cost/week =

Total cost/week =

Cost for 8 weeks =

POQ

LT= Week: Gross requirement Scheduled receipts 40 25 40 45 45 50 45 30 Projected on-hand 50 Net Requirement Planned rece

Total ending inventory =

No. of setup =

Carrying cost =

Setup cost =

Total cost =

Handle Clampa) Casting Base() Bracket Housing(2) Bearing(2) Spring(2) Shafta) Clamp (4) Handle) Casting(1) Bracket Base Spring Clamp Housing Handle Casting Bearing Shaft Gross requirement Available requirement 10 70 130 130 50 40 15 Net 5 70 Week: MPS for A MPS for B 1 100 2 200 100 3 80 100 4 100 5. 95 6 150 100 Lead Item time D E 3 2 2 Available Scheduled Receipts 100 400 1300 200 in week #1, 300 in week #2 400 in week #1, 300 in week #2 1000 in week #1, 1000 in week #2 C D E A E D E E3 B D3 E Item: Week: Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned releases order LT= 1 GR= 2 3 4 5 6 Item: Week: Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned releases Item: Week: order Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned releases order LT= 1 LT= 1 GR = 2 GR= 2 3 3 4 5 5 6 6 Item : Week: Gross requirement Scheduled receipts Projected on- hand Net Requirement Planned receipts Planned releases order LT= 1 GR= 2 3 4 5 6 Week: Gross requirement Scheduled receipts Projected on-hand 50 Net Requirement Planned receipts Planned order releases LT= 1 40 1 2 25 3 40 4 45 5 45 6 50 7 45 8 30 Week: Gross requirement Scheduled receipts Projected on-hand 50 Net Requirement Planned receipts Planned order releases LT= 1 2 25 1 40 3 40 4 45 5 45 6 50 7 45 8 30 Week: Gross requirement Scheduled receipts Projected on-hand 50 Net Requirement Planned receipts Planned order releases LT= 1 40 1 2 25 3 40 4 45 5 45 6 50 7 45 8 30

Step by Step Solution

3.38 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

The demand for subassembly S is 100 units in week 7 Each unit of S requires 1 unit of T and 2 units ... blur-text-image
Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management

Authors: Jay Heizer, Barry Render

10th edition

978-0136119418, 136119417, 978-0132163927

More Books

Students explore these related Mathematics questions

Question

What are seven tools of TQM?

Answered: 3 weeks ago