In Problem 8.14 it turns out that the project manager overestimated the project NPV, and the best

Question:

In Problem 8.14 it turns out that the project manager overestimated the project NPV, and the best estimate is that now $\mathrm{NPV}=\$ 2,444$ with a standard deviation of $\$ 1,500$. What is the probability that NPV could be 0 or less?

Data from problem 8.14

A project has an NPV of $\$ 3,444$ and a standard deviation of $\$ 1,780$. What is the probability that NPV could be 0 or less?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: