Solvent vessels must be purged before maintenance personnel enter in order to ensure that: (1) Sufficient oxygen

Question:

Solvent vessels must be purged before maintenance personnel enter in order to ensure that: 

(1) Sufficient oxygen is available for breathing; 

(2) Vapor concentrations are below the flash point; 

(3) Vapor concentrations are below the Occupational Safety and Health Administration (OSHA) limits if breathing apparatus is not to be used. 

Assuming that a 8 m3 fixed-roof solvent tank has just been drained of all liquid and that the vapor phase is initially saturated at 22°C, estimate the length of purge necessary with 2 m3/min of gas at 0.1 MPa and 22°C to reach the OSHA 8-hr exposure limit.

(a) Hexane 500 ppm

(b) 1-butanol 100 ppm

(c) Chloroform 50 ppm

(d) Ethanol 1000 ppm

(e) Toluene 200 ppm

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: