The following information is presented for the Marathon Manufacturing Company. Direct labor rate standard is $11.55.

Question:

The following information is presented for the Marathon Manufacturing Company.

• Direct labor rate standard is $11.55.

• Direct labor efficiency standard is 2.5 hours per finished unit.

• Budgeted production is 1,200 finished units.

• Production required 2,910 direct labor hours at a cost of $33,174.

• 1,150 finished units of product were produced.

Required:

a. Determine the direct labor rate variance.

b. Determine the direct labor efficiency variance in dollars.