Reconsider Problem 8.12, but now assume that the amount of resource 1 available and the amount of

Question:

Reconsider Problem 8.12, but now assume that the amount of resource 1 available and the amount of resource 2 available are both uncertain. In particular, each follows the normal distribution, with means equal to the original estimates of 8 and 4, respectively, but each with a standard deviation of 0.5. Use a chance constraint and Analytic Solver to find the maximum profit while requiring for each original constraint that there be at least a 95 percent chance of satisfying that constraint.


Data from Problem 8.12

Consider a resource-allocation problem having the following data:

 

The objective is to determine the number of units of each activity to undertake so as to maximize the total profit.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: