2.15. The opening backlog is 600 units. Forecast demand is as shown here. Calculate the weekly production

Question:

2.15. The opening backlog is 600 units. Forecast demand is as shown here. Calculate the weekly production for level production if the backlog is to be reduced to 200 units.

Week 1

2 3

4 5

6 Total Forecast Demand 700 750 700 750 700 800 Planned Production Projected Backlog 600 Answer. Total production = 4800 units Weekly production = 800 units Projected back log for week 1 = 500 units