2.16. The opening backlog is 1100 units. Forecast demand is as shown here. Calculate the weekly production

Question:

2.16. The opening backlog is 1100 units. Forecast demand is as shown here. Calculate the weekly production for level production if the backlog is to be increased to 1200 units.

Week 1

2 3

4 5

6 Total Forecast Demand 1200 1100 1200 1200 1100 1000 Planned Production Projected Backlog 1100

Fantastic news! We've Found the answer you've been seeking!