4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead

Question:

4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 As to be available in week 5.

There are 20 Bs available. All other on-hand balances = 0.

image text in transcribed

W eek 1 2 3 4 5 Part A G ross Requirements Scheduled Receipts Lead Time: 1 week Projected Available N et Requirements Planned Order Receipt Planned Order Release Part B Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available N et Requirements Planned Order Receipt Planned Order Release Part C Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part D Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part E Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part F Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Materials Management

ISBN: 9781292162355

8th Global Edition

Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive

Question Posted: