4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead
Question:
4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 As to be available in week 5.
There are 20 Bs available. All other on-hand balances = 0.
W eek 1 2 3 4 5 Part A G ross Requirements Scheduled Receipts Lead Time: 1 week Projected Available N et Requirements Planned Order Receipt Planned Order Release Part B Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available N et Requirements Planned Order Receipt Planned Order Release Part C Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part D Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part E Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part F Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release
Step by Step Answer:
Introduction To Materials Management
ISBN: 9781292162355
8th Global Edition
Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive