Question: 4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required

4.5. Given the following product tree, explode, offset, and determine the gross and net requirements. All lead times are 1 week, and the quantities required are shown in parentheses. The master production schedule calls for 100 As to be available in week 5.

There are 20 Bs available. All other on-hand balances = 0.

B(2) A DA C(1) D(1) E(1) D(2) F(1)

W eek 1 2 3 4 5 Part A G ross Requirements Scheduled Receipts Lead Time: 1 week Projected Available N et Requirements Planned Order Receipt Planned Order Release Part B Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available N et Requirements Planned Order Receipt Planned Order Release Part C Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part D Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part E Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release Part F Gross Requirements Scheduled Receipts Lead Time: 1 week Projected Available Net Requirements Planned Order Receipt Planned Order Release

B(2) A DA C(1) D(1) E(1) D(2) F(1)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Introduction To Materials Management Questions!