4.3. Using the following product tree, determine the planned order receipts and planned order releases if there
Question:
4.3. Using the following product tree, determine the planned order receipts and planned order releases if there are 50 As required in week 3 and 100 in week 5. All lead times are 1 week except for component E, which has a lead time of 2 weeks.
1 2 3 4 5 Part A Planned Order Receipt Lead Time: 1 week Planned Order Release Part B Planned Order Receipt Lead Time: 1 week Planned Order Release Part C Planned Order Receipt Lead Time: 1 week Planned Order Release Part D Planned Order Receipt Lead Time: 1 week Planned Order Release P a rtE Planned Order Receipt Lead Time: 2 weeks Planned Order Release