4.6. Complete the following table. Lead time for the part is 2 weeks. The lot size is...
Question:
4.6. Complete the following table. Lead time for the part is 2 weeks. The lot size is 50. In what periods should orders be released, and what should be the size of those orders?
1 2 3 4 5 6 7 Gross Requirements 20 30 50 50 20 30 10 Projected Available 70 Net Requirements Planned Order Receipt Planned Order Release