5.13. A work center has the following open and planned orders for week 4. Calculate the total...
Question:
5.13. A work center has the following open and planned orders for week 4. Calculate the total standard time required (load).
Order Quantity Setup Time (hours)
Run Time (hours/piece)
Total Time (hours)
Released Orders 110 250 2.00 0.20 220 200 2.50 0.15 Planned Orders 330 400 2.00 0.10 440 450 3.00 0.15 Total Time (standard hours)