Complete the following problem. The lead time is one week and the demand time fence is week
Question:
Complete the following problem. The lead time is one week and the demand time fence is week 3. There are 20 on hand. The lot size is 60.
Period Forecast Customer Orders Projected Available Balance MPS 20 1 2 3 4 5 6 20 21 22 20 28 25 19 18 20 18 30 22 ATP LO,1