Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size

Question:

Given the following data, calculate the projected available balance and the planned MPS receipts. The lot size is 100. The time fence is 2 weeks.

Week 1 2 3 4 Forecast 50 50 50 50 Customer Orders 60 30 60 20 Projected Available Balance 60 MPS LO,1