Complete the following table. Lead time for the part is two weeks, and the order quantity is
Question:
Complete the following table. Lead time for the part is two weeks, and the order quantity is 40. What action should be taken?
Week 1 2 3 4 Gross Requirements1 Projected Available 40 Net Requirements Planned Order Receipt Planned Order Release 20 15 10 20 LO.1