Using the following product tree, determine the planned order receipts and planned order releases if 200 As

Question:

Using the following product tree, determine the planned order receipts and planned order releases if 200 As are to be produced in week 5. All lead times are one week except for component E, which has a lead time of two weeks.

A B C D E Part A Lead Time: 1 week Planned Order Receipt Planned Order Release Week Part B Lead Time: 1 week Planned Order Receipt Planned Order Release Part C Lead Time: 1 week Planned Order Receipt Planned Order Release Part D Lead Time: 1 week Planned Order Receipt Planned Order Release Part E Lead Time: 2 weeks Planned Order Receipt Planned Order Release LO.1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction To Materials Management

ISBN: 9780132337618

6th Edition

Authors: J. R. Tony Arnold, Chapman, Stephen N., Lloyd M. Clive

Question Posted: