Suppose that the design engineer advises that he has a new design for component F. It wont

Question:

Suppose that the design engineer advises that he has a new design for component F. It won’t be ready until sometime after week 2, but he wants you to give a date for the first supplier shipment to come in, and you should be ready to tell the supplier how many to ship. Since the change is transparent to the customer, the design engineer advises you to go ahead and use up any existing material of the model. How will MRP help you to deal with this issue?