The opening backlog is 1100 units. Forecast demand is shown in the following. Calculate the weekly production

Question:

The opening backlog is 1100 units. Forecast demand is shown in the following. Calculate the weekly production for level production if the backlog is to be increased to 1200 units.

Week 1 2 3 4 5 6 Total Forecast Demand 1200 1100 1200 1200 1100 1000 Planned Production Projected 1100 Backlog LO.1