The opening backlog is 900 units. Forecast demand is shown in the following. Calculate the weekly production
Question:
The opening backlog is 900 units. Forecast demand is shown in the following. Calculate the weekly production for level production if the backlog is to be reduced to 200 units.
Week 1 2 3 4 5 6 Total Forecast Demand 600 700 700 700 600 500 Planned Production Projected 900 Backlog LO.1