In particular, enter the three estimates for each activity, and the template immediately will display the estimates

Question:

In particular, enter the three estimates for each activity, and the template immediately will display the estimates of the means and variances of the activity durations. After indicating each path of interest, the template also will display the approximate probability that the path will be completed within 22 months.