Reconsider Prob. 10.4-3, which involves trying to find the probability that a project will be completed by
Question:
Reconsider Prob. 10.4-3, which involves trying to find the probability that a project will be completed by the deadline.
Assume now that the duration of each activity has a triangular distribution that is based on the three estimates in the manner depicted in Fig. 22.10. Obtain a close estimate of the probability of meeting the deadline by performing 1,000 iterations of a simulation of the project on a spreadsheet. Generate the various available kinds of outputs similar to Fig. 22.12.