Question:
. Suppose that we have p = 4 quality char-
acteristics, and in correlation form all four variables have variance unity and all pairwise correlation coefficients are 0.7. The in-control value of the process mean vector is //' = [0, 0, 0, 0]. .
(a) Write out the covariance matrix E.
(b) What is the chi-square control Limit for the chart, assuming that Q =
0.01?
(c) Suppose that a sample of observa-
tions results in the standardized observation vector y = [3.5, 3,5, 3.5, 3.5]. Calculate the value of the TÂȘ statistic. Is an out-of-control sig-
nal gencrated?
(d) Calculate the diagnostic quantities di, i = 1, 2, 3, 4 from equation 10-22, Does this information assist in iden-
tifying which process variables bave shifted?
(e) Suppose that a sample of observa-
tions results in the standardized observation vector y' = [2.5, 2, - 1, 0]. Calculate the value of the T" sta-
tistic. Is an out-of-control signal generated?
(1) For the case in (e), calculate the diagnostic quantities di, I = 1, 2, 3, 4 from equation 10-22. Does this information assist in identifying which process variables have shifted?
Step by Step Answer: