Basic. A company has just secured a new contract which requires 500 hours of labour. There are
Question:
Basic. A company has just secured a new contract which requires 500 hours of labour.
There are 400 hours of spare labour capacity. The remaining hours could be worked as overtime at time-and-a-half or labour could be diverted from the production of product X. Product X currently earns a contribution of £4 in two labour hours and direct labour is currently paid at a rate of £12 per normal hour.
What is the relevant cost of labour for the contract?
(a) £200
(b) £1200
(c) £1400:
(d) £1800 ACCA - Financial Information for Management
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: