Intermediate: Contract costing HR Construction pic makes up its accounts to 31 March each year. The following
Question:
Intermediate: Contract costing HR Construction pic makes up its accounts to 31 March each year. The following details have been extracted in relation to two of its contracts:
Depreciation is charged on plant using the straight line method at the rate of 12% per annum.
Required:
(a) Prepare contract accounts, in columnar format, for EACH of the contracts A and B, showing clearly the amounts to be transferred to profit and loss in respect of each contract.
(20 marks)
(b) Show balance sheet extracts in respect of EACH contract for fixed assets, debtors and work in progress. (4 marks)
(c) Distinguish between job, batch and contract costing.
Explain clearly the reasons why these meth¬ ods are different.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: