Intermediate: Contract costing A construction company is currently undertaking three separate contracts and information relating to these
Question:
Intermediate: Contract costing A construction company is currently undertaking three separate contracts and information relating to these contracts for the previous year, together with other relevant data, is shown below.
The cost of operating the construction services department, which provides technical advice to each of the contracts, is apportioned over the contracts in proportion to wages incurred.
Contract STU is scheduled for handing over to the contractee in the near future and the site engineer estimates that the extra costs required to complete the contract in addition to those tabulated above, will total £138 000. This amount includes an allowance for plant depreciation, construction services and for contingencies.
Required:
(a) Construct a cost account for each of the three contracts for the previous year and show the cost of the work completed at the year end.
(9 marks)
(b) (i) Recommend how much profit or loss should be taken, for each contract, for the previous year. (7 marks)
(ii) Explain the reasons for each of your recommendations in
(b) (i) above.