WTFZ SE planned to manufacture 16,000 cutlery sets at a total cost of 80,000. Actual output, however,

Question:

WTFZ SE planned to manufacture 16,000 cutlery sets at a total cost of €80,000. Actual output, however, was only 12,000 sets at a total cost of €73,000.

1. Using the static method, calculate the variance between total cost charge-out and actual total cost and interpret the result.

2. Explain why the deviation between planned cost and actual cost cannot be further analyzed using a static plan.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question