Draw up a flexible budget for overhead expenses on the basis of the following data and determine
Question:
Draw up a flexible budget for overhead expenses on the basis of the following data and determine the overheads rates at 70%, 80% and 90% plant capacity:
At 70% capacity At 80% capacity At 90% capacity Variable overheads Indirect labour Rs 10,500 Rs 12,000 —
Stores including spares Rs 3,500 Rs 4,000 —
Semi-variable overheads Power Rs 18,250 Rs 20,000 —
Repairs and maintenance Rs 1,900 Rs 2,000 —
Fixed overheads Depreciation Rs 11,000 Rs 11,000 —
Insurance Rs 3,000 Rs 3,000 —
Salaries Rs 10,000 Rs 10,000 —
Total overheads Rs 58,150 Rs 62,000 —
Estimated direct labour hours 1,24,000 hours —
Step by Step Answer:
Related Book For
Question Posted: